← ARTEMIS TRACKER

LAUNCH DELAY HISTORY

Every time Artemis III's launch date has moved. Original target: 2024. Current target: 2028. That's 4 years of slip in 7 years of program existence.

4 YEARS
of schedule slip since the original 2024 target
Program has existed for 9 years. Slipped for 4 of them.

THE MOVING GOALPOST

March 2019→ 2024
VP Pence, National Space Council
Original "Moon by 2024" directive from the Trump administration
November 2021→ NET 2025
NASA Administrator Bill Nelson
Nelson acknowledged 2024 was "not feasible" citing HLS delays and congressional funding shortfalls
January 2022→ NET 2026
NASA OIG Report
Inspector General audit found Artemis III unlikely before April 2026 at the earliest
January 2024→ September 2026
NASA official update
Pushed again due to Starship HLS development timeline and Orion heat shield concerns from Artemis I
June 2024→ Mid 2027
GAO Assessment
GAO found schedule "under significant pressure" from HLS uncrewed demo landing not yet completed
January 2025→ NET Late 2027
NASA budget request
Pushed further pending Starship orbital refueling demo results
Early 2026→ NET September 2028
NASA program review
Current target — contingent on Starship HLS uncrewed lunar landing demo in 2027

THE PATTERN

Every 12-18 months, the launch date moves forward by another 12-18 months. The gap between "now" and "launch" never actually closes.

The primary bottleneck has shifted from SLS (which flew in 2022) to Starship HLS, which has never landed on the Moon, never demonstrated orbital refueling, and needs both before crew can fly.

NASA's own Inspector General has flagged the timeline as unrealistic in every annual report since 2021.